scheduling package - Urgent

Hi all gurus
If I create a package and schedule it for jobs and then if i delete the
package and create a new package with same name. Then my job for old package
will run on new package which has name of old deleted package?
In my case my old job runs new package.
will it make any problem?
Thanks
AMHuh?
"AM" <anonymous@.codecomments.com> wrote in message
news:Or0wyERRFHA.3544@.TK2MSFTNGP12.phx.gbl...
> Hi all gurus
> If I create a package and schedule it for jobs and then if i delete the
> package and create a new package with same name. Then my job for old
> package
> will run on new package which has name of old deleted package?
> In my case my old job runs new package.
> will it make any problem?
> Thanks
> AM
>
>|||AM,
If you create a DTS package, then schedule it, then delete the package, and
create a new one with the EXACT same name, your scheduled job will still wor
k.
Hope that answers your question.
Mark Allison, SQL Server MVP
http://www.markallison.co.uk
Looking for a SQL Server replication book?
http://www.nwsu.com/0974973602_.html
"AM" wrote:

> Hi all gurus
> If I create a package and schedule it for jobs and then if i delete the
> package and create a new package with same name. Then my job for old packa
ge
> will run on new package which has name of old deleted package?
> In my case my old job runs new package.
> will it make any problem?
> Thanks
> AM
>
>sql

scheduling package - Urgent

Hi all gurus
If I create a package and schedule it for jobs and then if i delete the
package and create a new package with same name. Then my job for old package
will run on new package which has name of old deleted package?
In my case my old job runs new package.
will it make any problem?
Thanks
AMHuh?
"AM" <anonymous@.developersdex.com> wrote in message
news:Or0wyERRFHA.3544@.TK2MSFTNGP12.phx.gbl...
> Hi all gurus
> If I create a package and schedule it for jobs and then if i delete the
> package and create a new package with same name. Then my job for old
> package
> will run on new package which has name of old deleted package?
> In my case my old job runs new package.
> will it make any problem?
> Thanks
> AM
>
>|||AM,
If you create a DTS package, then schedule it, then delete the package, and
create a new one with the EXACT same name, your scheduled job will still work.
Hope that answers your question.
--
Mark Allison, SQL Server MVP
http://www.markallison.co.uk
Looking for a SQL Server replication book?
http://www.nwsu.com/0974973602­.html
"AM" wrote:
> Hi all gurus
> If I create a package and schedule it for jobs and then if i delete the
> package and create a new package with same name. Then my job for old package
> will run on new package which has name of old deleted package?
> In my case my old job runs new package.
> will it make any problem?
> Thanks
> AM
>
>

scheduling package- Urgent

Hi all gurus
If I create a package and schedule it for jobs and then if i delete the
package and create a new package with same name. Then my job for old package
will run on new package which has name of old deleted package?
In my case my old job runs new package.
will it make any problem?
Thanks
AM
Huh?
"AM" <anonymous@.codecomments.com> wrote in message
news:Or0wyERRFHA.3544@.TK2MSFTNGP12.phx.gbl...
> Hi all gurus
> If I create a package and schedule it for jobs and then if i delete the
> package and create a new package with same name. Then my job for old
> package
> will run on new package which has name of old deleted package?
> In my case my old job runs new package.
> will it make any problem?
> Thanks
> AM
>
>
|||AM,
If you create a DTS package, then schedule it, then delete the package, and
create a new one with the EXACT same name, your scheduled job will still work.
Hope that answers your question.
Mark Allison, SQL Server MVP
http://www.markallison.co.uk
Looking for a SQL Server replication book?
http://www.nwsu.com/0974973602X.html
"AM" wrote:

> Hi all gurus
> If I create a package and schedule it for jobs and then if i delete the
> package and create a new package with same name. Then my job for old package
> will run on new package which has name of old deleted package?
> In my case my old job runs new package.
> will it make any problem?
> Thanks
> AM
>
>

Monday, March 12, 2012

Scheduled DTS Job Failed Urgent!

Hi All,

SQL Server 7
I have many DTS jobs running some of them have failed to run as per schedule time, when i try to run manually its giving the below error. pls see the below error
and help me as it is a case of urgency.

"Backup,CHECKALLOC,bulk copy, SELECT INTO,and file manipulation (such as CREATE FILE) operations on a database must be serialized. Reissue the statement after the current backup, CHECKALLOC, or file manipulation operation is completed."

The Scheduled backup has also failed. when i look at the job history details it gives
sqlmaint.exe failed (SQLSTATE 42000) (Error 22029). The step failed.First, check to make sure that all jobs are currently not running.

Next, disable non-essential jobs to quiesce activity.

Next, how large is the database? If not very large (<500MB), I would automatically run a DBCC CHECKDB just to make sure everything is okay. The only reason to consider database size here is that the CHECKDB command can take a long time to run. Your decision here will have to made based on your assessment of the business' need to get back on line.

Next, re-run your back up job. Make sure you get a clean run of the back-up process.

Finally, re-enable your DTS jobs. Look to see if you have any tasks within the DTS packages that run around the time of your backup that use some of the restricted functions/commands/statements. Focus on these packages first and see if they can be fixed or moved.

If you are backing up to tape, consider backing up to Disk. It is hundreds of time faster and will allow the backup job to complete more quickly.

HTH,
hmscott